CASE STUDY /
Project Ace
Relocation, Fit Out, Expansion

Overview:
We delivered the 140,000 sqft fit out of a speculative-build warehouse into a state-of-the-art food manufacturing and distribution facility within a 38 week programme.
Feasibility
Detailed Design
Construction
Commissioning
The Challenge:
The project included 80,000 sqft of freezer and fulfilment space, requiring specialist systems to maintain strict food safety and hygiene standards.
Delivered under a JCT Design & Build contract, it demanded tight coordination of design development, services installation and high-performance finishes to meet the specific needs of the food sector.
Working to a fast-track schedule, our team ensured full integration of temperature-controlled environments and operational systems without compromising on quality or compliance.
Location:
Blyth
Duration:
38 Weeks
Size:
140,000sqft
Value:
£14m
The Outcome:
Fit out of a speculative-build warehouse into a state-of-the-art food manufacturing and distribution facility within a 38-week programme.
The Feedback:
“We found the DDK team to be dedicated and flexible”
We worked with DDK on our latest expansion project in the UK. Though the project was complex and time bound, we found the DDK team to be dedicated and flexible, adapting well to the changing needs of the business and ultimately delivering a high standard of work.
Chief Operating Officer
UK Pet Food Manufacturer
Ready to Start Your Food Factory Construction?
Get in touch today to discuss how we can help bring your project to life.




