CASE STUDY /

Project Ace

Relocation, Fit Out, Expansion

Overview:

We delivered the 140,000 sqft fit out of a speculative-build warehouse into a state-of-the-art food manufacturing and distribution facility within a 38 week programme.

Feasibility

Detailed Design

Construction

Commissioning

The Challenge:

The project included 80,000 sqft of freezer and fulfilment space, requiring specialist systems to maintain strict food safety and hygiene standards.

Delivered under a JCT Design & Build contract, it demanded tight coordination of design development, services installation and high-performance finishes to meet the specific needs of the food sector.

Working to a fast-track schedule, our team ensured full integration of temperature-controlled environments and operational systems without compromising on quality or compliance.

Location:

Blyth

Duration:

38 Weeks

Size:

140,000sqft

Value:

£14m

The Outcome:

Fit out of a speculative-build warehouse into a state-of-the-art food manufacturing and distribution facility within a 38-week programme.

The Feedback:

“We found the DDK team to be dedicated and flexible”

We worked with DDK on our latest expansion project in the UK. Though the project was complex and time bound, we found the DDK team to be dedicated and flexible, adapting well to the changing needs of the business and ultimately delivering a high standard of work.

Chief Operating Officer

UK Pet Food Manufacturer