DDK transformed a 1970s building into a modern, fully operational food facility featuring multiple risk-zoned areas, all delivered to the highest standards of quality and compliance.
Feasibility
Detailed Design
Construction
Commissioning
The Challenge:
Delivering a large-scale fit out within an ageing structure required intricate planning to integrate new systems and layouts while meeting stringent food manufacturing and hygiene standards.
The project involved coordinating diverse risk-classified areas, high, low, and base-risk zones, as well as warehousing, each demanding tailored design and construction approaches.
Over the 55 week, £11 million programme, DDK managed complex logistics, regulatory requirements and sequencing to ensure a seamless transformation into a high-performing, compliant food production facility.
Location:
Sittingbourne
Duration:
55 weeks
Size:
70,000 sqft
Value:
£11,000,000
The Outcome:
Transformation of a 1970s building into a modern and fully operational food facility delivered to the highest standards of quality and compliance.